Construction Affects Pedestrian Traffic and Parking
Media Contact: , (859) 257-3303, x254
LEXINGTON, Ky. (Aug. 17, 2007) − With the fall 2007 semester about to
begin, students should be aware of current construction projects that are currently taking
place on the University of Kentucky campus, as these projects are affecting pedestrian walkways
as well as parking areas.
Replace Steam and Condensate Piping
Replace Steam and Condensate Piping
The sidewalk along the south side of UK Gatton College of Business & Economics will be closed
until Friday, Aug. 31. The contractor is currently working 10-hour shifts six days a week to
complete this construction as soon as possible. Signs will go up Thursday, Aug. 23, at multiple
locations around the Gatton College of Business & Economics and the Mathews Building directing
pedestrian traffic around the construction. These signs will also have maps of the area
identifying accessible routes and the construction zones to assist in directing
pedestrians. The Disability Resource
Center will inform students with disabilities and maintain an access map on the University
of Kentucky Web site during construction. The map can be accessed at http://kgsmap.uky.edu/website/AccessMap/viewer.htm
Renovate Third Floor of Lucille Little Fine Arts Library Building
Renovate Third Floor of Lucille Little Fine Arts Library Building
Construction is
ongoing on the third floor of the Lucille Caudill Little Fine Arts
Library, where there are currently three classrooms in use. The Registrar’s Office has been notified of the
construction as well as the schedule for the demolition of the elevator in early September. The
demolition of the elevator will impact accessibility to the third floor and portions of the
lower level. The first and second floors of the building are used for the Lucille Little Fine
Arts Library. The first floor is accessible from the plaza between Little Library and M. I.
King Library. Within the library space, a secondary elevator, serving only the first and second
floors, will remain in use. Also, a College of Fine
Arts computer lab classroom on the lower level has direct access from the outside. The
Registrar will relocate classes for the third floor classrooms as needed should there be a
faculty or student requiring an elevator.
Boone Center
Boone Center
The
first row of the “E” lot directly south of the rear of the Boone Center (accessed
off Columbia Avenue) is reserved for construction personnel and signage is posted. No other
impact is anticipated.
Student Health Facility
Student Health Facility
The Student Health Facility is
scheduled to be completed in April 2008. It is located at the northeast corner of South
Limestone and Rose Street. Sidewalks around the site will be maintained or temporarily
relocated during construction activities.
College of Pharmacy
College of Pharmacy
The walkway directly south of the Biomedical/Biological Sciences
Research Building (BBSRB), which connects Parking Structure 6 to the Kentucky Clinic, was closed last May and will
remain closed for the duration of the project. The project is currently scheduled for
completion by 2010.
Excavation operations are in progress and will
continue through September. Concrete foundations, consisting of some excavation as well, will
start early September and continue through March 2008. The location of the construction site is
directly north of Leader Avenue and directly west of Limestone where there was once an employee
parking lot.
The majority of Leader Avenue has been closed and will remain closed for the duration of the project. There is no vehicular traffic access to Leader via Limestone. There is vehicular access to the west end of Leader Avenue via Press Avenue, however this access is meant only to accommodate the tenants in the occupied apartments along Leader as there is no through traffic.
From Limestone to the west end of the construction site, the sidewalk just south of the BBSRB has been closed. A new sidewalk has been placed to connect the BBSRB service drive to Leader Avenue in order to re-route pedestrian traffic. The sidewalk along the south edge of Leader Avenue will remain open from Press Avenue to Limestone although it will be slightly re-routed around the construction site on the Limestone end. New lighting has been placed to illuminate this walkway.
Pedestrian traffic along the west edge of Limestone will remain open. A covered pedestrian walkway has been constructed along this sidewalk directly adjacent to the construction site.
Construction of the Patient Care Facility
The majority of Leader Avenue has been closed and will remain closed for the duration of the project. There is no vehicular traffic access to Leader via Limestone. There is vehicular access to the west end of Leader Avenue via Press Avenue, however this access is meant only to accommodate the tenants in the occupied apartments along Leader as there is no through traffic.
From Limestone to the west end of the construction site, the sidewalk just south of the BBSRB has been closed. A new sidewalk has been placed to connect the BBSRB service drive to Leader Avenue in order to re-route pedestrian traffic. The sidewalk along the south edge of Leader Avenue will remain open from Press Avenue to Limestone although it will be slightly re-routed around the construction site on the Limestone end. New lighting has been placed to illuminate this walkway.
Pedestrian traffic along the west edge of Limestone will remain open. A covered pedestrian walkway has been constructed along this sidewalk directly adjacent to the construction site.
Construction of the Patient Care Facility
The area between Agricultural Science Center
North (Ag North) and the hospital parking garage will be a major construction site for the
next three years. During the summer, three pedestrian pathways leading around and through the
site to campus will be maintained. As of early October, the pathway through the center of the
site will be closed to allow the beginning of excavation of the foundations of the new
hospital. The remaining pedestrian pathways around the perimeter of the site to main
campus via Limestone and South Campus via University Drive will be maintained for the duration
of the construction period. Both of these pathways are paved and
accessible.
The contractor is currently working six days a week.
Signs have been placed in the lobby of Ag North indicating the pathways for pedestrian traffic
around the construction. In addition, the contractor is installing signage along each pathway
providing direction and clearly defining the pedestrian pathways. These pathways are to remain
in service throughout the project.
Students with residential passes should
also note that with the completion of the Memorial Coliseum expansion, approximately 40 parking
spaces in the R1 lot (behind Memorial Coliseum) have been regained.